2016 Street Improvement Project - Minnewashta Manor Area

*Assessment Update*


At the October 9, 2017 City Council meeting, the Council approved a supplement to the assessment roll to extend the interest-free period to October 1, 2018 and move the additional deadlines back as follows:

  • Payment due to the City of Chanhassen Finance Department by October 1, 2018 and no interest will be collected.
  • Payment due to the City of Chanhassen Finance Department between     October 2, 2018 and December 31, 2018 and interest owed will be calculated from October 2 to the date paid.
  • If payment is not received by the City of Chanhassen Finance Department by     December 31, 2018, the assessments are to be proposed for a 10-year term at an interest rate of 5.75% to appear on the County tax statements. Interest will be collected each year based on the outstanding principal owed on the assessment.

Overview


This project includes the reconstruction of Minnewashta Manor neighborhood in the summer of 2017. The streets will be reconstructed to the existing width and concrete curb and gutter is proposed to be installed. The water main under the street and the water services from the water main to the property line will be replaced. Some sanitary sewer repairs will be completed within the reconstruction area. Stormwater management improvements will also be made.
bidresults.png

Bids were received and opened on Tuesday, December 6, 2016. Acceptance of bids and award of contract is scheduled for Monday, January 23, 2017 at which time the Bid Alternate will be approved.
 

Project Updates


October 10, 2017

Phase I
Week of 10/16: Backfilling, topsoil, landscaping (including irrigation and dog fence repairs), and sod placement will continue.
Week of 10/23: Remaining work to be finished up.

Phase II 
Week of 10/9: Road building on North Manor Road begins this week. Storm sewer work on Tanagers Lane will continue followed by road building.   
Week of 10/16: Finish Tanagers Lane followed by concrete curb and concrete driveway work.
Week of 10/23: Grading and paving.
Week of 10/30: Backfilling, topsoil, landscaping (including irrigation and dog fence repairs), driveways and sod placement will be talking place. 

*Work on Washta Bay Road will be delayed until next spring with completion planned for July, 2018.

NotifyMeKaren_thumb.png
Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule and upcoming construction activities. Contact Jean at 952-227-1162 or by email for assistance.
Project Notifications Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.