2016 Street Improvement Project - Minnewashta Manor Area

Overview


This project includes the reconstruction of Minnewashta Manor neighborhood in the summer of 2017. The streets will be reconstructed to the existing width and concrete curb and gutter is proposed to be installed. The water main under the street and the water services from the water main to the property line will be replaced. Some sanitary sewer repairs will be completed within the reconstruction area. Stormwater management improvements will also be made.
bidresults.png

Bids were received and opened on Tuesday, December 6, 2016. Acceptance of bids and award of contract is scheduled for Monday, January 23, 2017 at which time the Bid Alternate will be approved.
 

Project Updates

November 27, 2018

Due to equipment availability and weather, the rip-rap installation was delayed until the week of November 26.  Work should be completed by November 30.

November 7, 2018

This week and next, crews will be performing punch list work.  At the end of the week of November 12, rip-rap will be installed along the shoreline of 2941 Washta Bay Road.


October 2, 2018

The road will be patched in this week followed by paving of the final wear course the week of October 8, 2018 once the curb and gutter have had time to cure. 


September 26, 2018

Warranty work on the concrete curb and gutter should be done by the end of the week. The road will be patched in next week followed by paving once the curb and gutter have had time to cure.

Please Note: All schedules are weather permitting and may fluctuate in either direction of the anticipated dates. 

NotifyMeKaren_thumb.png
Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule and upcoming construction activities. Contact Jean at 952-227-1162 or by email for assistance.
Project Notifications Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.