Overview


The City is proposing to rehabilitate approximately 2 miles of streets as identified by it's Pavement Management software, site investigations and reported utility problems. This year's project includes several streets located in the Lake Susan Hills area.
bidresults.png

Project Updates


September 18, 2017 - Due to unforeseen delays, draintile work, backfilling, topsoil, landscaping, sod and driveway patching will be taking place this week and next week. Final paving of wearcourse to follow. 

Anticipated Project Schedule

Project Phase
Date
Approve Plans & Specifications
January 23, 2017
Bid Opening February 15, 2017
Assessment Hearing; Award of Contract March 27, 2017
Construction Start June 12, 2017
Substantial Completion August, 2017
NotifyMeKaren_thumb.png

NEW!

 Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule and upcoming construction activities. Due to the variability of construction, the updates typically do not include specific details such as day-to-day scheduled activity. The city's inspector will notify occupants directly if they will be impacted y a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.