Ithilien Pond Maintenance Project

Overview

The Ithilien Pond basin receives all the stormwater from the 20 homes in the Ithilien development, prior to its discharge into the Curry Farms Park ponds and eventually into Christmas Lake. The wetland has had significant amounts of sediment accumulation from stormwater runoff over the past 26 years. Maintenance of this basin is critical to prevent significant pollution from entering the lake, streams, and for flood control. The project is proposed to excavate sediment and grade the pond to the original contours.

Project Updates

Please check back for future updates.

January 17, 2019

The contractor will begin work on Monday, January 28.  Pond dewatering is scheduled for Tuesday, January 29, and tree removal is scheduled for Wednesday, January 30.  This schedule is weather dependent and subject to change.  Once the project commences, it should take approximately two weeks to complete.  Please use caution when traveling through the project area.

January 9, 2019

The contractor will be on site this week knocking down cattails in preparation for construction.  The actual construction start date will be dependent on the upcoming forecast.

December 27, 2018

The City has awarded the contract to Kusske Construction.  Work is anticipated to begin in mid-to-late January, weather dependent.  The work will take approximately three weeks to complete, with final restoration taking place in the Spring.

Project Notifications Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.