Highway 101 Improvements - Lyman Boulevard (CSAH 18) to Pioneer Trail (CSAH 14)
Overview
The City of Chanhassen, in cooperation with MnDOT and Carver County, completed a corridor scoping study for Highway 101 from Lyman Boulevard to the Scott County line in 2007. The study identified the segment of Highway 101 from Lyman Boulevard (CSAH 18) to Pioneer Trail (CSAH 14) as the highest priority for improvement. Improvements to this segment of Highway 101 are necessary to address existing safety deficiencies and to provide for the present and future traffic needs of the area. Reconstruction and widening of Highway 101 between Lyman Boulevard and Pioneer Trail include pedestrian/bicycle trails and a trail underpass. 

Road Closures/Openings
7/23/14 - Weather permitting, paving on Highway 101 south will take place on Saturday, July 26 and Monday, July 28, followed by striping on Tuesday. The roadway is tentatively scheduled to reopen on Wednesday, July 30. Signals should be operational on Thursday, July 31.

6/11/14 - Highway 101 south of Pioneer Trail will be reopened to traffic on Thursday afternoon. Simultaneously, Highway 101 from Lyman Boulevard to Pioneer Trail will be closed to through traffic for approximately 4 weeks to complete intersection work on the north side of Pioneer Trail and to reconstruct Highway 101 to 96th Street.

Access to Bandimere Park, Kiowa Trail and 96th Street will be provided from the north. The commuter traffic detour will use Lyman Boulevard to Powers Boulevard to Pioneer Trail.

4/29/14 - Beginning Monday, May 19, 2014, Highway 101 will be closed at Pioneer Trail with no access south of Pioneer Trail until approximately June 13, 2014. Beginning Monday, June 16, 2014, Highway 101 will be closed from Pioneer Trail north to 96th Street with no access south from Pioneer Trail through approximately July 11, 2014.  Detours will be posted for both closures.

Work on Highway 101 will continue after July 11, 2014 but will be completed under traffic with lane closures and/or temporary lane shifts. 

Project Layouts   
Schedule
 Award Construction Contract  April 22, 2013
 Anticipated 2014 Construction Startup  May 19, 2014
 Final Completion  September 12, 2014
         
Contact During Construction
Bob Schmidt
Kimley-Horn and Associates, Inc.
651-308-3805
Email


Sign up to receive project updates via email and text Sign up to receive project updates via email and text Sign up to receive project updates via email and text

Contact Us
Paul Oehme, P.E.
Director of Public Works/City Engineer
Email

Ph: (952) 227-1169
Fx: (952) 227-1170