City News

Posted on: September 13, 2017

Road Closure Information

RoadClosureICON.png












HWY 41 (Hazeltine Blvd) 

Begin: Tuesday, September 12

Duration: 2-3 weeks, weather dependent 

Overview: Southbound lane on HWY 41 at HWY 5 will be closed for utility work by CenterPoint Energy. 

Click for detour map


Park Road/Park Place

Begin: Monday, September 18

Duration: 4 weeks

Overview: Full road closure west of IWCO buildings to replace box culvert underneath the street. 

Click for more information and for contacts and detour map.


Yosemite Ave

Begin: Monday, September 18

Duration: 1 week

Overview: Closure located just north of Lake Lucy Road intersection. Contractor for Anthem on the Park will be doing work in the area. Traffic will be detoured to Powers Blvd. 


HWY 101/61 Causeway Bridge 

Begin: Monday, October 2

Duration: 3.5 weeks. Planned to be complete by Friday, October 27. 

Overview: The contractor for the Southwest Regional Reconnection Project plans to install deck sealer for the HWY 101 causeway bridge. Although there are no planned closures of HWY 101, there will by only 1 lane in each direction open to traffic. 

Click for more information

Facebook Twitter Google Plus Email

Other News in City News