2016 Street Rehabilitation Project
Overview
The City is proposing to rehabilitate approximately 1.4 miles of streets as identified by it's Pavement Management software, site investigations and reported utility problems. This year's projects include several streets located in the Fox Chase and Lone Cedar areas.

Anticipated Project Schedule
Public Hearing; Order Plans & Specifications
           February, 2016            
Approve Plans & Specifications; Order Ad for Bids
March, 2016            
Assessment Hearing
May 9, 2016            
Project Begins
June, 2016            
Substantial Completion
August 30, 2016            