Audubon Road Reconstruction Project 10-02
The project includes the reconstruction of Audubon Road from Lake Drive West to Lyman Boulevard, the installation of turn lanes, concrete curb and gutter, storm sewer and a 10-foot wide bituminous trail on the west side from Valley Ridge Trail North to Lyman Boulevard. Based on the bid amount, the total project cost is $1,964,994.37 ($795,005.63 below the original estimate). Click HERE to view an updated copy of the plan.
Click HERE to view the May 24, 2010 City Council staff report accepting bids/awarding contract/holding the assessment hearing.
Click HERE to view the June 29, 2010 construction notice regarding Audubon Road access.
CONSTRUCTION NOTICE UPDATE 6/30/10: During the upcoming holiday weekend, limited access to Audubon Road north of Valley Ridge Trail North, and to Audubon Road south of Valley Ridge Trail South will remain open; however, due to the rough condition of the gravel section, the City is requesting that residents and visitors use Osprey Lane as much as possible. Click HERE to view the June 29, 2010 construction notice regarding Audubon Road access which includes a detour map.
NOTICE OF STREET ACCESS CHANGE 8/16/10: At 9:00 a.m. on Thursday, August 19, 2010, access to Valley Ridge Trail North, Valley Ridge Trail South, Valley View Court, Valley View Place, Valley Ridge Court and Valley Ridge Place will be switched to Valley Ridge Trail South. Please use Valley Ridge Trail South to Audubon Road south to Lyman Boulevard. The Valley Ridge Trail South access will remain in effect until the projected project completion date in mid-September. Please refer to Facebook, the City of Chanhassen Website or the Construction Hotline (952-227-1326) for any changes.
If you have any questions or concerns, please contact Construction Manager Gordy Stauff at 952-215-9412. Thank you for your continued patience during the project.
Project Schedule (weather permitting)
- June, 2010
- Small utility (eg. power, cable, phone) relocation begins
- Tree removal
- Begin storm sewer installation
- July, 2010
- Start grading - the contractor will begin in the area between Heron Drive and Valley Ridge Trail South
- August, 2010
- Install curb and gutter
- Begin paving
- Substantial construction completion: September 2, 2010
Neighborhood Meetings
- May 20, 2010
- January 13, 2010
If you have any questions regarding this project, please contact Alyson Fauske at 952-227-1164 or by email at afauske@ci.chanhassen.mn.us.
NOTE: Please be advised that any comments received via email will become public record and included in the staff report for this item.
This page was last updated on July 1, 2010.
|
|