2018 Street Improvement Project - Orchard Lane Area

Overview


This proposed project includes the reconstruction of streets in the Orchard Lane area in the summer of 2019. The proposed project includes replacement of water main under the street and water services from the water main to your property line, sanitary sewer repairs and stormwater management improvements. Pavement of West 64th Street will be rehabilitated with spot curb and gutter repairs along with replacement of a section of water main.

Project Schedule


Public Hearing October 22, 2018
Council Approves Plans & Specifications; Orders Ad for Bid              November 13, 2018              
Public Information Meeting January 2019
Assessment Hearing; Award of Contract January 28, 2019
Construction Begins April 2019
Substantial Completion September 2019
Final Completion June 2020
NotifyMeKaren_thumb.png
Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule and upcoming construction activities. Contact Sara at 952-227-1162 or by email for assistance.
Project Notifications Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.