2021 City Pavement Rehabilitation Project

20-05 Project Areas Map
  1. Matt Petite

    Engineering Technician/ Construction Manager
    Phone: (952) 227-1166 Cell: (612) 358-7085

  2. George Bender

    Assistant City Engineer
    Phone: (952) 227-1164

Notify Me Button
Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates.  The information will be general in nature, such as proposed project schedule and upcoming construction activities.  Contact Stacy at 
952-227-1162 or by email for assistance.

Overview

The adoption of a new franchise fee has allowed the City to invest substantially more in the maintenance and preservation of our local roads, which can be seen from the scope of the 2021 City Pavement Rehabilitation project. This project will incorporate multiple roadway treatments (mill & overlay, full depth reclamation, etc.) depending on the condition of the road for each area, along with minor spot repairs on existing utilities.

A total of seven (7) miles of roadway is proposed to be improved, so the project has been broken up into six areas; the Lake Lucy Road area (east of Powers Boulevard), Choctaw Circle area, Kurvers Point Road area, Marsh Drive area, Redwing Lane area, and the Trappers Pass area. The project is anticipated to begin in the summer of 2021, with work scheduled to be completed in the fall of 2021. Residents that utilize the streets within the project areas will be notified if access is limited.

This project was originally planned for 2020, however In light of recent state funding losses stemming from the COVID-19 pandemic and out of concern for the potential negative economic impact assessments might have on some Chanhassen residents, the City Council voted to postpone the planned road construction project and reassess at a later time.  It is now scheduled to take place during the 2021 construction season.

Click Here for a full map of the project areas.


Related Resources

Assessment Practice
The City of Chanhassen's Assessment Practice is intended to provide direction to City Staff in preparation of assessment rolls for public improvements, to ensure fair and consistent treatment of all properties within the City of Chanhassen.

Pavement Management
Pavement Management Questions/Answers


Project Updates

June 18, 2021

Please see below, under Project Areas, for updated construction dates for each neighborhood area. 

June 17, 2021

Lake Lucy Road Area: Reclaiming operations for the road will begin on Monday, June 21st and Tuesday, June 22nd. They will then remove the excess gravel, grade, re-compact, and water the gravel base section the remainder of the week.  Paving of the new bituminous base section is planned to occur on Tuesday, June 29 or Wednesday, June 30.  Topsoil placement, restoration of irrigation systems and pet fences, along with landscaping work will occur mostly after the paving of the base section but some may occur prior to the paving.  Placement of the final lift of bituminous section will occur after the 4th of July. Please have vehicles off the street from 7am to 6pm if possible so they are not potentially in the way when reclaiming, grading, and paving operations are ongoing. Please proceed with caution, slow down, and drive safely.

Redwing Lane Area: Water main work has been completed and no shutoffs of the water main are scheduled moving forward, thank you for your patience. Storm sewer work is ongoing for this week and into next week. Curb and gutter removals will occur at the end of next week and replacement of the curbing is planned for the following week as well as other tasks such as adjusting structures. The Contractor currently plans to hold off milling the bituminous surface until after the 4th of July. Please proceed with caution, slow down, and drive safely.

 

Previously Posted Updates


Project Areas

This project is divided into six neighborhood areas. Trappers Pass is the largest area and will be divided into two construction phases.

Here are the Estimated Construction Dates for Each Area:

Lake Lucy Road areaMay 17 - July 15
Redwing Lane areaJune 11 - July 24
Choctaw Circle areaJune 22 - Aug 5
Trappers Pass-1 area (See Map)June 30 - Oct 7
Trappers Pass-2 area (See Map)July 26 - Oct 7
Marsh Drive areaAug 16 - Oct 29
Kurvers Point Road areaAug 30 - Oct 28

Substantial completion is expected by November 2021.  Stormwater pond clean-out work will occur in the Trapper's Pass area during the winter of 2021/2022.  Final restoration is planned during the spring of 2022. 

Project Schedule

Revised for 2021 Project Start
Accept Feasibility Report/Call Public HearingJanuary 11, 2021
Public HearingJanuary 25, 2021
Approve Plans & Specifications/Authorize BiddingFebruary 8, 2021
Bid OpeningMarch 12, 2021
Public Information Open HouseApril 14, 2021
Assessment Hearing/Award ContractApril 26, 2021
Start ConstructionMay 2021
Substantial CompletionNovember 2021
Project Notification Disclaimer
Due to the variability of construction, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they will be impacted by a utility service shut down (example: water shutoff), or work (such as excavation or new curb) that will impede access to the property for a period of hours or days.